|
US 93: Wickenburg to Santa Maria River Location/Design Concept Study and Environmental Studies
|
|
SR 89 to Wickenburg Interim Bypass |
Steering Committee Meeting Minutes - September 16, 1999 Location and Time: Wednesday, September 16, 1999 1:00 p.m. Hassayampa River Preserve Conference Room Participants:
Subject: US 93, Wickenburg to Santa Maria River Location/Design Concept Study TRACS No. 093 YV 161 H4871 01 L Steering Committee Meeting
MEETING SUMMARY:
Bert Bertleson opened the meeting by providing a project status report. ADOT/Sverdrup was continuing to work on field surveys (environmental), completing the hydrologic studies, and preparing to fly the northern half of the project for aerial photogrammetry and topographic mapping. The evaluations for the corridors, both interim and ultimate, were also progressing, including cost estimates and comparisons between major corridor features (qualitative and quantitative). A copy of the project scoping report was distributed for the committee members information. The report includes the information gathered from the agency and public scoping meetings. Following the status report, Mr. Bertleson led an informal sharing of information and comments. The purpose of the Steering Committee (SC) was again addressed, noting that this gathering was to be a two-way exchange of information. It is not a public meeting, nor is it intended to be a press conference. All members of the SC are encouraged to share ideas, participate in the discussions, and make suggestions for improving the concepts presented. Since the study process is a discovery process, information presented will continue to be studied and revised to best fit the needs of the Wickenburg project. With respect to the study schedule, Mr. Bertleson noted we were on schedule for a late October / early November public meeting to present the results of our alternatives analysis. Mr. Bertleson distributed copies of an evaluation matrix of the three bypass corridors. Evaluation factors were separated into three categories:
Questions/Comments raised during the discussion included the following: Horizontal Alignment:
Vertical Alignment:
Access:
Constructibility:
Cost:
Land Use Consistency:
Rehabilitation Centers:
Right-of-Way:
Section 4(f) Involvement:
Noise Impacts:
General comments:
Mr. Bertleson noted that following the results of this analysis, the NE corridor is not a likely candidate for the bypass. He had also requested that comments on the evaluation be submitted to Sverdrup within a 1 week.
Mr. Bertleson led a discussion on the probability of funding the various improvement projects. Initially, the interim improvement projects were envisioned to be $1-5 Million in size. Upon further evaluation, most of the alternatives resulted in $13-20 Million in cost. These size projects will compete with other major highway improvements across the State and within the County, and would not likely be funded for the next 10 years. The balance of the bypass improvements would then follow these "interim" projects, but no estimate could be made as to when these projects would be completed. A new alternative was presented for the interim improvements: Build two lanes of the ultimate bypass to tie US 60 north to US 93, along the alignment of the ultimate bypass route. This improvement would include the interim improvements at Wickenburg Way and Tegner proposed by "Alternative 10", and include a modification of the R/R underpass just west of the Tegner intersection. This alternative would actually begin the construction of the bypass, and solve the truck problems in the downtown area. This new alternative met strong objections from Royce Kardinal for the following reasons:
Rusty Gant offered the following:
Bill Green offered the following:
Dana Burden offered the following:
Jim Liggett offered the following:
After additional debate about the merits of each alternative, it was agreed that further discussion should be postponed until more input on outstanding issues could be presented. A meeting with the BLM was being arranged to determine the extent of the 4(f) issues on the two western bypass routes. A traffic analysis was being completed that compares the traffic capacities of the three (# 4, 7 & 10) interim solutions. This analysis would determine how long each proposed improvement could sustain the projected traffic loads.
Due to the late hour, this discussion item was postponed to the next Steering Committee Meeting. The meeting adjourned at approximately 5:00 p.m.. Several committee members expressed appreciation for the opportunity to discuss freely the issues presented at the meeting. Next Meeting: The next steering committee meeting was scheduled for: October 7, 1999 from 1:00 to 5:00 p.m.at the Hassayampa River Preserve. |
|