|

Home
SR 89 to
Wickenburg Interim Bypass
Wickenburg (SR 89) to Santa Maria
River
Interim Improvement Project
Wickenburg
Bypass
Related Studies
Study Team
Feedback
What's New



| |
Steering Committee Meeting Minutes - April 25,
2000
Location and Time:
Tuesday, April 25, 2000 1:00 p.m.
Hassayampa River Preserve Conference Room
Participants:
| Organization |
Representative |
Participating Alternate |
| ADOT |
Rich DeBoer |
|
| Sverdrup Civil |
Bert Bertleson |
|
| Bureau of Land Management |
Mike Taylor |
Angela Mogel |
| Maricopa County |
Mike Sabatini |
Tim Oliver |
| Yavapai County |
Richard Straub |
Gay Hendin (absent) |
| State Land Department |
Sheila McCafferty (Absent) |
|
| Town of Wickenburg Elected |
Rusty Gant |
|
| Town of Wickenburg Staff |
Fred Carpenter |
|
| Wickenburg School District #9 |
Doug Price |
|
| Chamber of Commerce Business |
Royce Kardinal |
|
| Chamber of Commerce Transportation Committee |
Bill Green |
|
| Homeowners Northeast |
Jim Liggett |
|
| Homeowners Southwest |
Andy Anderson |
|
| B.O.O.T. |
Jim Dickinson |
|
| Recreation Groups |
Richard Wertz |
|
| Hassayampa River Preserve |
Mike Rigney |
|
Subject: US 93, Wickenburg to Santa Maria River
Location/Design Concept Study
TRACS No. 093 YV 161 H4871 01 L
Steering Committee Meeting
MEETING SUMMARY:
- Open Comments:
The meeting opened at approximately 1:10 with an opportunity for
committee members to ask any questions before getting into the agenda items. The following
issues/questions were raised:
J. Dickinson: The Arizona Department of Environmental
Quality (ADEQ) is proposing a remediation project at the Vulture Mine Superfund Site near
Motel 8 Downtown. They (ADEQ) have referred to Alternative 13 as a "Bypass" that
would go through the site. B. Bertleson noted that Sverdrup was aware of ADEQs work
and had been in contact with the ADEQ project manager. The reference to "bypass"
by ADEQ is incorrect and they have been informed as such.
R. Gant: What is the projected end date of the study? B.
Bertleson noted that 1 year away is still the target, although several additional issues
have been raised since the project inception that may delay completion until Fall, 2001.
R. Wertz: Tom Foster has said that the interim project up
the river is a foregone conclusion. In addition to the new alignment, both existing
Hassayampa River bridges could be replaced with a single 5-lane in addition to the
structures required for the interim project. B. Bertleson noted that Tom might be looking
at issues that face the ADOT District that are outside the limits of this studys
scope.
-
Review / Approve 12/14/99 Meeting Minutes: Bertleson summarized what was covered at
the last meeting, including the following key points:
- The BLM was invited to participate in the committee. Mike Taylor presented the
BLMs position on the corridor study and alternatives analysis.
- The study process does not address funding priorities. However, due to the magnitude of
the bypass cost and a shortfall of funds for the projects statewide, the committee needs
to be aware of the potential affects on implementing the bypass construction.
- An evaluation of the interim alternatives through town is continuing.
- The public meeting was postponed due to the need to look at the bypass corridors in
greater detail and further evaluate several BLM concerns.
The minutes of the 12/14/99 meeting were recommended for approval by
Bill Green and seconded by Andy Anderson. By vote, the minutes were approved.
- Project Status Report:
B. Bertleson summarized the progress completed since the
previous steering committee meeting. Key points included:
- Efforts have focused on the bypass area for specific alignment options within the
single, wide, southern corridor.
- Engineering evaluations are completed to a point, awaiting agency environmental input.
- Meetings were held with the BLM to discuss evaluation criteria.
- The goal is for a Public Meeting in early summer.
- Field investigations are ongoing for drainage studies
- The Southwest (SW) and Farwest (FW) corridors, although combined into a single study
corridor, each have an identified alignment that is being evaluated further. Currently,
there is no preferred alternative.
- Fieldwork and evaluations have begun on the Interim DCR (Alternatives 7 & 13).
- Alternatives have been identified north of Wickenburg, between SR 89 and the Santa Maria
River crossing. These will continue to be developed further.
- Bypass Corridor Evaluations
(see exhibit slides attached): A presentation was made
by Berwyn Wilbrink on the evaluation of the bypass corridors. At the previous steering
committee meeting, the SW and FW corridors were combined into a single corridor for
evaluation. Within this corridor, 7 alignments were developed (horizontally and
vertically). The seven corridors were evaluated using the following criteria:
- Corridor Width (Evaluate opportunities to develop independent roadways to best fit the
landform).
- Grade (Evaluate need for truck climbing lanes).
- Earthwork (Need for deep cuts through hills and high embankments in fill areas).
- Drainage (type and size of structures).
- Constructability (possibilities for staged construction as well as site access).
After evaluating the alignments, two alternatives stood out as desired
bypass solutions that met the geometric objectives.
Alternative F is located within the old SW corridor and
is the most northerly alignment. It begins by crossing the Hassayampa River south of the
Preserve, near the RR bridge crossing. It generally follows the northern boundaries of the
BLM land on the north side of the Vulture Mountains. As the alignment passes Vulture Mine
Road, it is hidden in a valley between Twin Peaks and a series of knolls located south of
the Flying E Ranch. As the alternative heads north, it is located east of Black Mountain
and west of Black hill.
Alternative G is located within the old FW corridor and
is the most southerly alignment. It begins by crossing the Hassayampa River south of
Alternative F where the footprint of the river is wider, but the topography is not as
rugged. This alternative heads west following the south side of the Vulture Mountain
foothills to a saddle located just south of Vulture Peak. It is located generally 2 to 3
miles south of the BLMs northern boundary. After crossing Vulture Mine Road, it
turns to head north following the south side of the Twin Peaks foothills. As the
alternative approaches US 60, it is located west of Black Mountain and west of Black hill.
A preliminary video simulation of a flight above both alternatives was
presented.
Don Smith described the environmental evaluation of the alternatives.
They included:
- Visual Impacts
- Noise Impacts (to Trails, Parks)
- Habitat Fragmentation
- Habitat Reduction/Degradation
- Reduced Recreation Opportunities
- Severance to Jeep/Hiking Trails
- Intrinsic Values (Impact on pristine environment)
While the engineering evaluation is quantifiable, the environmental
evaluation includes features that are more qualitative and more difficult to achieve a
consensus. There are many users of the BLM lands that must be considered. The users
include the area residents as well as those from the Metropolitan Phoenix area. This
evaluation is not complete and is on going.
Following the presentation, several comments were made as follows
(responses are in italics):
- Alternative F is too close to the Hassayampa River Preserve. Although it is closer
than G, the alignment is not inside the Preserve.
- Drainage impacts to the Preserve need to be evaluated from both alternatives where
highway drainage could drain directly into the Preserve.
- The visual aesthetics of the current RR bridge crossing of the Hassayampa should be
evaluated compared to the new crossing of Alternative F. The new crossing could destroy a
scenic treasure.
- The vertical alignment of the southern alternative is flatter than the northern
alternative.
- Still need to evaluate how the northern connection to US 93 will tie into SR 89.
- The northern alternative is much closer to the Flying E and Los Cab. Resorts.
- Will a noise/vibration study be performed with respect to proximity to anything? D. Smith
noted that FHWA has noise criteria identified for residences/hospitals/ parks/etc. The
most restrictive criteria is 67dB before mitigation is required for noise abatement.
Vibration is not an impact evaluation criteria.
- Wildlife may be more sensitive to noise than the current standards indicate. ADOT may
need to evaluate the noise and with more scrutiny towards the delicate nature of the
Preserve.
- Vibration / Noise over the new bridges should also be considered. D. Smith noted that
since noise carries further than vibrations, the noise is the greater concern.
- What is the cost per mile of the alternatives? The approximate cost per mile through
mountainous terrain is $8-10 million. Each alignment will be estimated in greater detail,
including bridge, drainage, earthwork, and pavement costs.
- There are many trails north of the Vulture Mountains that are used daily by two guest
ranches. These will be impacted by Alternative F.
- The town desires that any alternative selected be located on the east side of Black
Mountain so it will coincide with the industrial parks planned.
- As noted during the scoping meetings, neither of the two alternatives should have a
Traffic Interchange (TI) at Vulture Mine Road. While the current concept does not
include one, the BLM and State Lands may desire access to their lands and resources from
that location.
B. Bertleson noted that the evaluations will be completed and presented
to the ID Team for review and comment. They will decide which of the following scenarios
will be carried forward:
- Option 1:The two alignments are too close by comparison to pick a clear preferred
alignment at this time. Both will be carried forward to the public review process and
evaluated in more detail.
- Option 2:Following this evaluation series, there is enough information to determine that
one alignment is preferred and it will be carried forward for detailed design concept
development and evaluation.
- Interim Improvement Projects
: B. Bertleson provided an overview of the interim
projects.
Alternative 10 (see attached exhibit) is being scoped in a Project
Assessment (PA). Minor modifications to the intersection of Tegner and Wickenburg Way will
improve the capacity of the intersection to meet the traffic needs for the next 10 years.
This improvement is not a "final" answer to the congestion problems but an
economical solution until a higher capacity roadway is constructed. The PA document will
provide scope, cost and implementation information should the alternative be programmed
for construction. It was agreed that Alternative 10 would not be implemented unless agreed
upon mutually by ADOT and the Town.
The Transportation Oversight Committee has already met with ADOTs
Randy Blake to discuss improvements at the intersection. These discussions included added
left turn signals and removing crosswalks. The crosswalks are a feature that restrict
efficient timing of the lights. However, many disagree with Randy that they should be
considered for removal due to the heavy school use they get. Improvements to the
intersection will be scoped as part of the preparation of the PA.
Alternatives 7 and 13 (or a variation thereof) will be considered in a
separate Design Concept Report. The two options (see attached exhibits) will be developed
further, presented to the public for comment, and subsequently one selected as the
recommended plan for improving traffic conditions until the ultimate bypass south of town
can be funded and constructed.
J. Dickinson added that another alternative should be included in the
evaluation. He desires that a one-way couplet be considered. This option would have NB
traffic use Kerkes/Yavapai Streets and use Tegner Street for the SB movements. A one way
couplet was considered as one of the initial alternatives for providing a short-term
solution (Alternative 8). While it has some merits, the critical turning movement at the
existing intersection with US 60 and US 93 does not change. In addition, NB traffic would
be winding through narrow streets and mix with community center, chopping center and town
hall traffic. It also does not meet the Towns traffic circulation plan. This
alternative was again dropped from further consideration.
Following the descriptions of the three alternatives (10, 7 & 13),
the committee provided scoping issues, concerns and objectives that pertain to each
alternative.
Alternative #10
- Cross-walk safety for pedestrians.
- Retain small town aesthetics to draw people downtown. Appearance is a high priority.
- The iron barriers proposed earlier are not desired.
- Operationally, even if restriped, some doubt if two 18-wheelers can turn simultaneously.
- Concerns with the number of kids that use the intersection for school access.
- Barriers could give many a false sense of security, especially kids.
- If the parking is removed, concerns that the speed will rise.
- The existing church nearby may become a charter school, adding to the children traffic.
- The improvements are a step up for traffic, but a step down for the community.
- Have the Town make the decision when the modifications are implemented.
- Should be limited in time, not part of any final solution.
- Improvements should allow cross traffic at Apache Street to cross. If the
Tegner/Wickenburg Way signal delays traffic further, this situation will also get worse.
- The modified intersection during off-peak hours could encourage locals to drive even
faster than they do today.
- If the street-side parking is removed, a plan should be made to provide for the lost
spaces to the area businesses.
- Perhaps a traffic signal is required at Yavapai.
- Many locals turn left at Valentine to avoid the delays at Tegner.
- Will ADOT consider a bridge for pedestrians?
- Many oppose this concept entirely.
- Barriers will prohibit patrons from entering/seeing businesses.
Alternative #7
- Concept opposed by BOOT membership for the following:
- New bridge across Hassayampa
- New levy in river
- Unsightly from west bank of Hassayampa
- Makes using Yavapai Street difficult
- Concept is tougher on east-side residents
- Impedes hospital access
- Doubt if locals want it
- Raise in speeds likely
- Increase in noise to local residents
- Contrary to BOOT, several are in favor of the alternative.
- Does match local traffic patterns.
- Still requires a sharp right turn for NB traffic and a sharp left for SB.
- Concerns for impacts to adjacent neighborhoods.
- Concerns for impacts to business economy downtown.
- The Town Hall is not in the flood plain.
- Does not match the ultimate circulation plan for the community.
- Impacts to the upstream/downstream river need to be evaluated.
- Armoring will be required around the bridge abutments. Evaluations must include impacts
of the armoring on the Preserve and other downstream features.
- The height of the berm (roadway embankment) will be unsightly.
- Will it provide enhanced flood protection to those west of the berm, and will it worsen
the impacts to those on the east bank?
- Will involve similar situation at Kerkes as there is today at Tegner.
- Will economically impact property values on the east side of town greater than those on
the west.
- Will increase noise to downtown.
- How will traffic be controlled during construction?
- A 2-lane roadway fits the needs of the Town better.
- Prefer modifications to keep the Wishing Well in tact.
- Encourage business parking at the Town Center.
- The wishing well, although not on a historic register, is an attraction.
Alternative #13
- Opposed by BOOT even more so than Alternative 7.
- Will be opposed by east side residents.
- Offers greater visual challenges than Alternative 7.
- Adversely effects the businesses on the east side more than the businesses on the west.
- Will reduce property values on the east side.
- Has all of the issues of Alternative #7, and more
- Is consistent with what the town has planned for future traffic circulation.
- Towns plan was to develop a road on east side of river anyway.
- Saves the wishing well site.
- The selection should be made by Town officials
this is the type of thing they were
elected to do for the community.
- It appears to have the greatest environmental impacts.
- The intersection at the east end does not look operationally feasible
- The alignment is removed from the neighborhoods that Alternative 7 is adjacent to.
- The drainage issues are compounded by the addition of another river crossing.
- Might encourage ADOT to abandon funding of the bypass that provides other benefits.
- Alternative is supported by Town officials and Chamber of Commerce.
- Public Meeting Presentation
: The information presented today will continue to be
refined for presentation to the public. The public meeting will include an explanation of
the bypass and interim improvements, along with the evaluations of both. It will also
present a recommendation. Having enough information to present a clear recommendation has
been the key factor that has held up the public meeting.
The public meeting will likely be held in early summer. Prior to the
meeting, we will discuss our presentation to the Steering Committee for their comment.
-
Open Discussion :
Dick Wertz:
One other alternative should be presented: a two-lane truck route built on the ultimate
bypass alignment. This should be constructed without spending any money on Alternatives
10, 7 or 13.
Prepare an update of all costs on the various alternatives discussed to date to make a
true comparison of the options before the town.
With no other discussion items, and the late hour, the meeting
adjourned at 5:00 p.m.
|