Preliminary
Structure Selection Report - Hassayampa River Bridge (June 2004).
Evaluation of structure type, layout, cost, and function for the new
Hassayampa River Bridge.
Preliminary
Structure Selection Report - Sols Wash Bridge (June 2004). Evaluation of
structure type, layout, cost, and function for the new Sols Wash Bridge.
Final Design Concept Report (October 2003). Describes the
engineering details of the recommended design concept.
Final Environmental Assessment (September 2003). This document is an addendum to the Draft EA.
Draft Environmental Assessment (June
2002). This document
summarizes the alternatives development process and assesses the potential social,
economic, and environmental impacts associated with the proposed
project.
Project Assessment for Alternative 10 (April 2001). This document
assesses the requirements to implement Alternative 10.
Feasibility Report
(February 2000). This report documents the initial evaluation of
the original 13 interim improvement alternatives.
Scoping Report (September
1999) This report
compiles all of the information collected during the scoping process.
|